Tim R. Snoke,
Secretary-Treasurer
As part of a long-term effort to reduce basement backups and sewer overflows, MSD Project Clear is constructing approximately 4,580 feet of sewer in the Citys of Sunset Hills and Crestwood. The East Watson Sanitary Relief project will increase the size of the wastewater sewer which will reduce basement backups and prevent sewer overflows in this area. Construction is scheduled to begin in Spring of 2021 with anticipated completion in the Fall of 2022.
View May 11, 2021 Project Presentation Public Meeting
MSD is investing $1.54 million into the Cities of Crestwood and Sunset Hills with this project to alleviate basement backups and clean up our local waterways.
MSD’s contractor, Above and Below Contracting, will install the pipe by digging through the surface, a process known as “open-cut.” The contractor will dig a trench several feet into the ground, remove the old sewer pipe, and replace it with a newer, larger pipe. They will work section-by-section, and will fill completed sections with gravel or cover with steel plates to reduce traffic disruptions.
With any construction, residents can expect to see and hear heavy equipment during the sewer excavation process. The pictures above depict what a neighborhood will look like before, during, and after a typical project.
Because some of the construction takes place in the roadway, customers may experience lane restrictions or temporary road closures during working hours. MSD will have a traffic mitigation plan to ensure residents have access to homes and businesses.
Some residents may experience temporary access restrictions to their driveways. The contractor will give all property owners ample notification prior to access restrictions and will ensure access during non-working hours.
At least one MSD Inspector will be on-site part of the day for every day the contractor is working.
This is the current tentative project schedule. This is subject to change based on a variety of factors including weather.
Previous milestones:
After the contractor installs all new pipes, they will restore the construction site according to all local and District requirements. Properties with temporary construction easements will be restored per the signed easement agreements. Properties with existing easements will be restored to a clean condition such as sodding disturbed areas and replacing disturbed pavement.